Centre Pier

Back To Map
  • Approximately 19,800 m3 LLRW in the Temporary Storage Site – COMPLETED 2018
  • Approximately 32,000 m3 LLRW
  • Property owned by the Municipality of Port Hope, currently leased to Cameco Corporation

 

Remediation/Restoration Plans
  • Removal of the Temporary Storage Site and all buildings on Centre Pier
  • Topsoil and mulch will be placed on the previously excavated area and erosion control blankets will be placed and staked as required
  • Final grades will be attained with backfill materials and graded to permit surface water runoff
  • Waste will travel along the South Transportation Route to the Long-Term Waste Management Facility
  • Final restoration to be developed in consultation with stakeholders and Municipality of Port Hope Waterfront Plan